Progress

Overall
101/111 sub-tasks done · 97%
97% done
Repair and seal roof
3/3
Repair damaged walls and ceiling upstairs
6/6
Change location of walls
12/12
Relocate outer door
9/9
Rebuild the bathroom floor
7/7
Reinforce the bedroom floor
6/6
Rebuild the upstairs floor
16/16
Renovate the main bathroom
15/17
Finish crawl space
10/10
Cleanup
17/25

Project

Description
Repair of roof and water damage, upstairs renovation, and structural rebuild of the upper floors.
Work started
11 May 2026
Duration
154 days

Client

Name
Serena Epstein
Phone
WhatsApp

Location

Address
Travessa 5 de Outubro 6
Salir do Porto 2500-692
Property type
Residential

Tasks

Task Area Work type Status Est. Photos Notes
Repair and seal roof 3/3
Replace the broken roof tiles
Roof Roofing Done 3 days +5
Repair gutters
Roof Roofing Done 2 days
Seal roof to prevent future water intrusion
Roof Roofing Done 2 days +1
Repair damaged walls and ceiling upstairs 6/6
Repair the water-damaged ceiling walls & in bedroom
Bedroom Plastering Done 1 day +6
Repair the water-damaged walls & ceiling in bathroom
Bathroom Plastering Done 1 day
Repair the water-damaged walls & ceiling in other upstairs areas
Upstairs Plastering Done 2 days +3
Repaint walls and ceiling in bedroom
Upstairs Painting Done 3 days
Repaint ceiling in bathroom
Bathroom Painting Done 2 days
Repaint walls and ceilings in other upstairs areas
Bedroom Painting Done 2 days +1
Change location of walls 12/12
Demolish the interior walls
Upstairs Demolition Done 3 days +1
Demolish the second bathroom
Upstairs Demolition Done 3 days
Rebuild bathroom walls
Bathroom Plastering Done 4 days +4
Create opening for bathroom door
Bathroom Plastering Done 2 days +2
Create opening for bedroom door
Bathroom Plastering Done 1 day
Redo plumbing (shower, bathtub, sink, toilet)
Upstairs Plumbing Done 5 days
Redo electrical (recessed lights, switches, outlets)
Upstairs Plumbing Done 3 days
Reinstall AC unit
Upstairs Electrical Done 0.5 days
Rehang mirror and connect to electricity
Bedroom Electrical Done 0.25 days Plugged into wall
Install bathroom door
Bathroom Plastering Done 0.5 days
Install bedroom door
Bedroom Plastering Done 0.5 days
Rebuild ceiling in laundry room
Laundry room Plastering Done 1 day
Relocate outer door 9/9
Remove the old door
Upstairs Windows & doors Done 1 day
Create opening for the new door
Upstairs Demolition Done 2 days +2
Install concrete beams for the door frame
Upstairs Masonry Done 3 days +3
Install door threshold
Upstairs Masonry Done 1 day +1
Install new door
Outside Masonry Done 1 day +5
Close up old door opening
Upstairs Masonry Done 1 day
Put shelves in old door opening
Upstairs Masonry Done 2 days
Paint exterior wall around door
Outside Painting Done 1 day
Install door handles and lock
Outside Finishing Done 0.25 days
Rebuild the bathroom floor 7/7
Demolish old bathroom floor
Bathroom Demolition Done 3 days +2
Remove the dining room ceiling
Living room Demolition Done 3 days +5
Rebuild the floor with concrete blocks
Bathroom Masonry Done 3 days +1
Cement infill on the floor
Bathroom Masonry Done 3 days +2
Finish the dining room ceiling
Living room Plastering Done 3 days +3
Build the new bathroom wall
Bathroom Masonry Done 2 days
Redo electrical wiring (light switches, outlets, electric towel rail)
Bathroom Electrical Done 2 days
Reinforce the bedroom floor 6/6
Remove the living room ceiling
Bedroom Carpentry Done 3 days +4
Reinforce the worm-damaged beams with new beams
Bedroom Carpentry Done 3 days
Treat the wood
Bedroom Finishing Done 1 day
Add insulation to ceiling
Living room Insulation Done 1 day +1
Rebuild the living room ceiling
Living room Plastering Done 2 days +1
Repaint the ceiling and walls
Living room Painting Done 3 days
Rebuild the upstairs floor 16/16
Demolish old floor
Upstairs Demolition Done 3 days +16
Add two support pillars and an iron beam
Living room Masonry Done 7 days
Add arch to support pillars
Living room Plastering Done 3 days +10
Remove door and add arch
Living room Plastering Done 1 day +3
Redo electrical downstairs
Living room Electrical Done 3 days
Add 28-30 treated timber beams
Upstairs Carpentry Done 5 days
Apply 22mm OSB
Upstairs Flooring Done 2 days +3
Apply the waterproofing membrane
Upstairs Insulation Done 1 day
Apply sound dampening layer
Upstairs Insulation Done 1 day
Rebuild the spare room ceiling
Spare room Plastering Done 2 days
Rebuild the downstairs bathroom ceiling
Living room Plastering Done 1 day
Paint downstairs walls & ceilings
Living room Painting Done 5 days +1
Apply second layer of OSB
Upstairs Flooring Done 2 days
Install vinyl plank flooring
Upstairs Flooring Done 3 days
Install 4 ceiling lights downstairs
Living room Electrical Done 1 day +5 Bruno needs to come back with parts
Replace damaged tile on floor and bottom of walls
Living room Flooring Done 1 day +6
Renovate the main bathroom 15/17
Replace skylight
Bathroom Masonry Done 2 days +1
Create built-in shelves
Bathroom Plastering Done 0 days
Lay the bathroom flooring
Bathroom Flooring Done 2 days
Tile the bathroom walls
Bathroom Plastering Done 5 days +3
Install the bathtub
Bathroom Plumbing Done 2 days +2
Install access panel for bathtub
Bathroom Plastering Done 0.5 days
Reinstall shower
Bathroom Plumbing Done 1 day
Reinstall toilet
Bathroom Plumbing Done 0.5 days
Reinstall sink
Bathroom Plumbing Done 0.5 days
Reinstall mirror
Bathroom Electrical Done 0.25 days
Install heated towel rail
Bathroom Electrical Done 0.25 days Apparently this is up to Daniel because he planned the mounting location on the wall; needs to be mounted above outlet
Finish outlets and light switches
Bathroom Electrical Done 0.5 days
Install ventilation
Bathroom Electrical Done 0.5 days +2 Outside still uncovered. Need fan with switch, not sensor.
Move light switch to other side of door
Bathroom Electrical Unstarted 1 day
Wire bathroom mirror to light switch
Bathroom Electrical Unstarted 0.5 days
Fix sink tap
Bathroom Plumbing Done 0.25 days
Fix bathtub tap
Bathroom Plumbing Done 0.25 days
Finish crawl space 10/10
Open wall
Upstairs Demolition Done 1 day
Apply OSB
Bedroom Flooring Done 1 day
Finish doorway
Upstairs Masonry Done 1 day
Add concrete to level the floor in doorway
Upstairs Flooring Done 0.25 days
Install 3 recessed lights
Upstairs Electrical Done 1 day
Install 2 outlets
Upstairs Electrical Done 1 day
Install 1 light switch
Upstairs Electrical Done 0.5 days
Plasterboard ceilings & walls
Upstairs Plastering Done 2 days
Paint ceilings & walls
Upstairs Painting Done 2 days
Install vinyl plank flooring
Upstairs Flooring Done 1 day
Cleanup 17/25
Move furniture back into living room
Living room Finishing Done 0.5 days
Reverse order of light switches in living room
Living room Electrical Done 0.25 days
Re-hang 7 shelves
Living room Finishing Done 1 day +4 Serena did this herself
Move furniture back into bedroom
Bedroom Finishing Done 0.5 days
Move furniture back into other upstairs area
Upstairs Finishing Done 0.5 days
Fix new door open/close
Upstairs Finishing Done 0.25 days Door hits door frame when opening & closing
Fix big sliding glass door (lots of debris in the track)
Living room Finishing Done 0.25 days
Fix light in downstairs bathroom
Bathroom Electrical Done 0.25 days
Reinstall curtain rod and curtain in downstairs bathroom
Bathroom Finishing Done 0.25 days
Repair hole in ceiling
Living room Plastering Done 0.5 days
Stack washing machine and dryer
Laundry room Finishing Done 0.5 days
Fix spare room door (doesn't open properly)
Spare room Finishing Unstarted 0.25 days
Remove scratches from wood desk
Living room Finishing Unstarted 0.25 days
Re-hang curtain rod
Living room Finishing Unstarted 0.25 days
Clean coffee room in annex
Annex Finishing Unstarted 0.25 days
Repair damage to desk in annex
Annex Finishing Unstarted 0.25 days
Remove all equipment and materials
Outside Finishing In progress 1 day
Clean debris and dirt
Outside Finishing In progress 1 day
Replace damaged & missing items (bucket, mop, hose, shower rod, shower curtain)
Outside Finishing Unstarted 0.25 days +2
Paint unfinished areas of outer wall
Outside Painting Done 1 day
Repair cracks in doorway
Living room Plastering Done 0.25 days
Reconnect washing machine
Laundry room Plumbing Done 0.5 days
Finish top of bathroom door
Bathroom Windows & doors Done 0.25 days Top of bathroom door is completely unfinished and hollow
Seal gaps below baseboards
Upstairs Flooring Done 0.5 days
Fix air conditioner
Upstairs Electrical Done 1 day After being moved, AC unit only blows air, it does not cool air

Invoices

Invoiced
58,727.00 €
Paid
57,338.20 €
Outstanding
1,388.80 €
Paid: 57,338.20 € / 58,727.00 €
InvoiceDate AmountPaid Status
0030-26 23 Feb 2026 3,800.00 € 3,800.00 € Paid in full
0085-26 16 Apr 2026 7,625.00 € 7,625.00 € Paid in full
0099-26 15 May 2026 9,000.00 € 9,000.00 € Paid in full
0119-26 3 Jun 2026 23,600.00 € 23,600.00 € Paid in full
0122-26 5 Jun 2026 5,100.00 € 5,100.00 € Paid in full
0134-26 20 Jun 2026 2,900.00 € 2,900.00 € Paid in full
0147-26 7 Jul 2026 3,230.00 € 3,230.00 € Paid in full
0182-26 7 Aug 2026 3,472.00 € 2,083.20 € Partial payment

Decisions & agreements

Date Decision
15 May 2026 The living room ceiling will be rebuilt, along with the related structural extras (0099-26).
6 Jun 2026 The rest of the upstairs floor will be rebuilt in timber (0119-26), not in concrete over a new load-bearing wall; a waterproof concrete layer will go over the OSB.
6 Jun 2026 The quotes will be paid without VAT.
9 Jun 2026 Júlio will guarantee the work for 3 years, not 2.
22 Jun 2026 A 20×20 iron H-beam and two 15 mm iron pillars will be built to support the living room ceiling; the arched doorway is included (0134-26).
17 Jul 2026 The pillars and arches will be finished in render, not plasterboard, so heavy shelves can be mounted.
3 Aug 2026 The bathroom skylight will be replaced with a larger one (1000×800) rather than opening a window in the wall.
10 Aug 2026 The bathroom door will be moved back to its original location (so it does not overlap with ceiling and the old sink can still fit)