| Task | Area | Work type | Status | Est. | Photos | Notes | |
|---|---|---|---|---|---|---|---|
|
Repair and seal roof
3/3
|
|||||||
|
Replace the broken roof tiles
|
Roof | Roofing | Done | 3 days | +5 | ||
|
Repair gutters
|
Roof | Roofing | Done | 2 days | |||
|
Seal roof to prevent future water intrusion
|
Roof | Roofing | Done | 2 days | +1 | ||
|
Repair damaged walls and ceiling upstairs
6/6
|
|||||||
|
Repair the water-damaged ceiling walls & in bedroom
|
Bedroom | Plastering | Done | 1 day | +6 | ||
|
Repair the water-damaged walls & ceiling in bathroom
|
Bathroom | Plastering | Done | 1 day | |||
|
Repair the water-damaged walls & ceiling in other upstairs areas
|
Upstairs | Plastering | Done | 2 days | +3 | ||
|
Repaint walls and ceiling in bedroom
|
Upstairs | Painting | Done | 3 days | |||
|
Repaint ceiling in bathroom
|
Bathroom | Painting | Done | 2 days | |||
|
Repaint walls and ceilings in other upstairs areas
|
Bedroom | Painting | Done | 2 days | +1 | ||
|
Change location of walls
12/12
|
|||||||
|
Demolish the interior walls
|
Upstairs | Demolition | Done | 3 days | +1 | ||
|
Demolish the second bathroom
|
Upstairs | Demolition | Done | 3 days | |||
|
Rebuild bathroom walls
|
Bathroom | Plastering | Done | 4 days | +4 | ||
|
Create opening for bathroom door
|
Bathroom | Plastering | Done | 2 days | +2 | ||
|
Create opening for bedroom door
|
Bathroom | Plastering | Done | 1 day | |||
|
Redo plumbing (shower, bathtub, sink, toilet)
|
Upstairs | Plumbing | Done | 5 days | |||
|
Redo electrical (recessed lights, switches, outlets)
|
Upstairs | Plumbing | Done | 3 days | |||
|
Reinstall AC unit
|
Upstairs | Electrical | Done | 0.5 days | |||
|
Rehang mirror and connect to electricity
|
Bedroom | Electrical | Done | 0.25 days | Plugged into wall | ||
|
Install bathroom door
|
Bathroom | Plastering | Done | 0.5 days | |||
|
Install bedroom door
|
Bedroom | Plastering | Done | 0.5 days | |||
|
Rebuild ceiling in laundry room
|
Laundry room | Plastering | Done | 1 day | |||
|
Relocate outer door
9/9
|
|||||||
|
Remove the old door
|
Upstairs | Windows & doors | Done | 1 day | |||
|
Create opening for the new door
|
Upstairs | Demolition | Done | 2 days | +2 | ||
|
Install concrete beams for the door frame
|
Upstairs | Masonry | Done | 3 days | +3 | ||
|
Install door threshold
|
Upstairs | Masonry | Done | 1 day | +1 | ||
|
Install new door
|
Outside | Masonry | Done | 1 day | +5 | ||
|
Close up old door opening
|
Upstairs | Masonry | Done | 1 day | |||
|
Put shelves in old door opening
|
Upstairs | Masonry | Done | 2 days | |||
|
Paint exterior wall around door
|
Outside | Painting | Done | 1 day | |||
|
Install door handles and lock
|
Outside | Finishing | Done | 0.25 days | |||
|
Rebuild the bathroom floor
7/7
|
|||||||
|
Demolish old bathroom floor
|
Bathroom | Demolition | Done | 3 days | +2 | ||
|
Remove the dining room ceiling
|
Living room | Demolition | Done | 3 days | +5 | ||
|
Rebuild the floor with concrete blocks
|
Bathroom | Masonry | Done | 3 days | +1 | ||
|
Cement infill on the floor
|
Bathroom | Masonry | Done | 3 days | +2 | ||
|
Finish the dining room ceiling
|
Living room | Plastering | Done | 3 days | +3 | ||
|
Build the new bathroom wall
|
Bathroom | Masonry | Done | 2 days | |||
|
Redo electrical wiring (light switches, outlets, electric towel rail)
|
Bathroom | Electrical | Done | 2 days | |||
|
Reinforce the bedroom floor
6/6
|
|||||||
|
Remove the living room ceiling
|
Bedroom | Carpentry | Done | 3 days | +4 | ||
|
Reinforce the worm-damaged beams with new beams
|
Bedroom | Carpentry | Done | 3 days | |||
|
Treat the wood
|
Bedroom | Finishing | Done | 1 day | |||
|
Add insulation to ceiling
|
Living room | Insulation | Done | 1 day | +1 | ||
|
Rebuild the living room ceiling
|
Living room | Plastering | Done | 2 days | +1 | ||
|
Repaint the ceiling and walls
|
Living room | Painting | Done | 3 days | |||
|
Rebuild the upstairs floor
16/16
|
|||||||
|
Demolish old floor
|
Upstairs | Demolition | Done | 3 days | +16 | ||
|
Add two support pillars and an iron beam
|
Living room | Masonry | Done | 7 days | |||
|
Add arch to support pillars
|
Living room | Plastering | Done | 3 days | +10 | ||
|
Remove door and add arch
|
Living room | Plastering | Done | 1 day | +3 | ||
|
Redo electrical downstairs
|
Living room | Electrical | Done | 3 days | |||
|
Add 28-30 treated timber beams
|
Upstairs | Carpentry | Done | 5 days | |||
|
Apply 22mm OSB
|
Upstairs | Flooring | Done | 2 days | +3 | ||
|
Apply the waterproofing membrane
|
Upstairs | Insulation | Done | 1 day | |||
|
Apply sound dampening layer
|
Upstairs | Insulation | Done | 1 day | |||
|
Rebuild the spare room ceiling
|
Spare room | Plastering | Done | 2 days | |||
|
Rebuild the downstairs bathroom ceiling
|
Living room | Plastering | Done | 1 day | |||
|
Paint downstairs walls & ceilings
|
Living room | Painting | Done | 5 days | +1 | ||
|
Apply second layer of OSB
|
Upstairs | Flooring | Done | 2 days | |||
|
Install vinyl plank flooring
|
Upstairs | Flooring | Done | 3 days | |||
|
Install 4 ceiling lights downstairs
|
Living room | Electrical | Done | 1 day | +5 | Bruno needs to come back with parts | |
|
Replace damaged tile on floor and bottom of walls
|
Living room | Flooring | Done | 1 day | +6 | ||
|
Renovate the main bathroom
15/17
|
|||||||
|
Replace skylight
|
Bathroom | Masonry | Done | 2 days | +1 | ||
|
Create built-in shelves
|
Bathroom | Plastering | Done | 0 days | |||
|
Lay the bathroom flooring
|
Bathroom | Flooring | Done | 2 days | |||
|
Tile the bathroom walls
|
Bathroom | Plastering | Done | 5 days | +3 | ||
|
Install the bathtub
|
Bathroom | Plumbing | Done | 2 days | +2 | ||
|
Install access panel for bathtub
|
Bathroom | Plastering | Done | 0.5 days | |||
|
Reinstall shower
|
Bathroom | Plumbing | Done | 1 day | |||
|
Reinstall toilet
|
Bathroom | Plumbing | Done | 0.5 days | |||
|
Reinstall sink
|
Bathroom | Plumbing | Done | 0.5 days | |||
|
Reinstall mirror
|
Bathroom | Electrical | Done | 0.25 days | |||
|
Install heated towel rail
|
Bathroom | Electrical | Done | 0.25 days | Apparently this is up to Daniel because he planned the mounting location on the wall; needs to be mounted above outlet | ||
|
Finish outlets and light switches
|
Bathroom | Electrical | Done | 0.5 days | |||
|
Install ventilation
|
Bathroom | Electrical | Done | 0.5 days | +2 | Outside still uncovered. Need fan with switch, not sensor. | |
|
Move light switch to other side of door
|
Bathroom | Electrical | Unstarted | 1 day | |||
|
Wire bathroom mirror to light switch
|
Bathroom | Electrical | Unstarted | 0.5 days | |||
|
Fix sink tap
|
Bathroom | Plumbing | Done | 0.25 days | |||
|
Fix bathtub tap
|
Bathroom | Plumbing | Done | 0.25 days | |||
|
Finish crawl space
10/10
|
|||||||
|
Open wall
|
Upstairs | Demolition | Done | 1 day | |||
|
Apply OSB
|
Bedroom | Flooring | Done | 1 day | |||
|
Finish doorway
|
Upstairs | Masonry | Done | 1 day | |||
|
Add concrete to level the floor in doorway
|
Upstairs | Flooring | Done | 0.25 days | |||
|
Install 3 recessed lights
|
Upstairs | Electrical | Done | 1 day | |||
|
Install 2 outlets
|
Upstairs | Electrical | Done | 1 day | |||
|
Install 1 light switch
|
Upstairs | Electrical | Done | 0.5 days | |||
|
Plasterboard ceilings & walls
|
Upstairs | Plastering | Done | 2 days | |||
|
Paint ceilings & walls
|
Upstairs | Painting | Done | 2 days | |||
|
Install vinyl plank flooring
|
Upstairs | Flooring | Done | 1 day | |||
|
Cleanup
17/25
|
|||||||
|
Move furniture back into living room
|
Living room | Finishing | Done | 0.5 days | |||
|
Reverse order of light switches in living room
|
Living room | Electrical | Done | 0.25 days | |||
|
Re-hang 7 shelves
|
Living room | Finishing | Done | 1 day | +4 | Serena did this herself | |
|
Move furniture back into bedroom
|
Bedroom | Finishing | Done | 0.5 days | |||
|
Move furniture back into other upstairs area
|
Upstairs | Finishing | Done | 0.5 days | |||
|
Fix new door open/close
|
Upstairs | Finishing | Done | 0.25 days | Door hits door frame when opening & closing | ||
|
Fix big sliding glass door (lots of debris in the track)
|
Living room | Finishing | Done | 0.25 days | |||
|
Fix light in downstairs bathroom
|
Bathroom | Electrical | Done | 0.25 days | |||
|
Reinstall curtain rod and curtain in downstairs bathroom
|
Bathroom | Finishing | Done | 0.25 days | |||
|
Repair hole in ceiling
|
Living room | Plastering | Done | 0.5 days | |||
|
Stack washing machine and dryer
|
Laundry room | Finishing | Done | 0.5 days | |||
|
Fix spare room door (doesn't open properly)
|
Spare room | Finishing | Unstarted | 0.25 days | |||
|
Remove scratches from wood desk
|
Living room | Finishing | Unstarted | 0.25 days | |||
|
Re-hang curtain rod
|
Living room | Finishing | Unstarted | 0.25 days | |||
|
Clean coffee room in annex
|
Annex | Finishing | Unstarted | 0.25 days | |||
|
Repair damage to desk in annex
|
Annex | Finishing | Unstarted | 0.25 days | |||
|
Remove all equipment and materials
|
Outside | Finishing | In progress | 1 day | |||
|
Clean debris and dirt
|
Outside | Finishing | In progress | 1 day | |||
|
Replace damaged & missing items (bucket, mop, hose, shower rod, shower curtain)
|
Outside | Finishing | Unstarted | 0.25 days | +2 | ||
|
Paint unfinished areas of outer wall
|
Outside | Painting | Done | 1 day | |||
|
Repair cracks in doorway
|
Living room | Plastering | Done | 0.25 days | |||
|
Reconnect washing machine
|
Laundry room | Plumbing | Done | 0.5 days | |||
|
Finish top of bathroom door
|
Bathroom | Windows & doors | Done | 0.25 days | Top of bathroom door is completely unfinished and hollow | ||
|
Seal gaps below baseboards
|
Upstairs | Flooring | Done | 0.5 days | |||
|
Fix air conditioner
|
Upstairs | Electrical | Done | 1 day | After being moved, AC unit only blows air, it does not cool air | ||
| Invoice | Date | Amount | Paid | Status | |
|---|---|---|---|---|---|
| 0030-26 | 23 Feb 2026 | 3,800.00 € | 3,800.00 € | Paid in full | |
| 0085-26 | 16 Apr 2026 | 7,625.00 € | 7,625.00 € | Paid in full | |
| 0099-26 | 15 May 2026 | 9,000.00 € | 9,000.00 € | Paid in full | |
| 0119-26 | 3 Jun 2026 | 23,600.00 € | 23,600.00 € | Paid in full | |
| 0122-26 | 5 Jun 2026 | 5,100.00 € | 5,100.00 € | Paid in full | |
| 0134-26 | 20 Jun 2026 | 2,900.00 € | 2,900.00 € | Paid in full | |
| 0147-26 | 7 Jul 2026 | 3,230.00 € | 3,230.00 € | Paid in full | |
| 0182-26 | 7 Aug 2026 | 3,472.00 € | 2,083.20 € | Partial payment |
| Date | Decision | |
|---|---|---|
| 15 May 2026 | The living room ceiling will be rebuilt, along with the related structural extras (0099-26). | |
| 6 Jun 2026 | The rest of the upstairs floor will be rebuilt in timber (0119-26), not in concrete over a new load-bearing wall; a waterproof concrete layer will go over the OSB. | |
| 6 Jun 2026 | The quotes will be paid without VAT. | |
| 9 Jun 2026 | Júlio will guarantee the work for 3 years, not 2. | |
| 22 Jun 2026 | A 20×20 iron H-beam and two 15 mm iron pillars will be built to support the living room ceiling; the arched doorway is included (0134-26). | |
| 17 Jul 2026 | The pillars and arches will be finished in render, not plasterboard, so heavy shelves can be mounted. | |
| 3 Aug 2026 | The bathroom skylight will be replaced with a larger one (1000×800) rather than opening a window in the wall. | |
| 10 Aug 2026 | The bathroom door will be moved back to its original location (so it does not overlap with ceiling and the old sink can still fit) |